ON-SITE WASTEWATER INSPECTION REPORT
Permit Number: OSP211215 PID Number: C9.5-0 — i`�I/
- 6S_
Dwelling: X Single Family (SF) ❑ with ADU ❑ Duplex (D) ❑ Two Single Family Project: ■❑ New ❑ Upgrade
Name
Laura Trejo
ABSORPTION FIELD
0 Deep Trench ❑ Wide Trench ❑ Bed ❑ Mound
Site Address
20900 Upper Lowland Ave. Eagle River, AK
❑ Other
Phone
Number of Bedrooms
Soil Rating
depth from original grade
907-357-6760
4
1.2 GPD/SF
JTotal
8.5' Ft.
LEGAL DESCRIPTION
Depth to pipe invert from original grade
2,5' Ft.
Gravel depth beneath pipe
6 Ft.
Subdivision Block Lot
Uplands Phase 3 --- Lot 2
Fill added above original grade
4' Ft.
Gravel length
45' Ft.
Township Range Section
Gravel width
2' Ft.
Beds: Number of Lines
0
Distance between lines
Ft.
SEPARATION
DISTANCES
To
Septic
Absorption
Lift Station
Holding
Sewer
Total absorption area
Number of trenches
Dist. between trenches
From
Tank
Field
Tank
Line
540 Ft z
1
Ft.
Well
_
_
_
_
_
TANK X Septic ❑ S.T.E.P. ❑ Holding ❑ Other
Manufacturer
Greer Tank
Capacity
1250 Gal.
Surface Water
1001+
1001+
_
_
Material
Number of compartments
Lot Line
53'
8'
-
-
NA
HDPE
2
Foundation
12'
13'
_
( _
LIFT STATION
Manufacturer
Capacity
Remarks The area has been graded and stabilized with a BFM and seed.
Gal.
Existing well located on property to the south about 155' from tank
Alarm location
Electrical installed by
PIPE MATERIAL House to tank 3034 Tank to
drainfield 3034
Installer
Anderson Construction & Engineering
ALL PIPE PVC ASTM 3034 Drainfield 3034 CO/MT3034
Inspector Scott Pyle (TBC)
BENCH MARK (Assumed elevation) 806.95 ft
Inspeection
1-` 6/23/2021 6/25/2021
Location and description
2nd
ction
3b 6/25/21 41h 10/18/2$
NW building corner hub
ON-SITE WATER AND WASTEWATER SECTION APPROVAL
Engineer's Stamp
Conditional Approval: Date
1-'oo.`49
m ;;�,q-�''-='--;
d
of
TI"AQTHY.1.ALLEY �� m
►p �, .� ,o/ E 313
Septic S stem
Approve Date � ZZ
Note: this approval does not include well permit requirements.
tKev u5ru2n6t
RECORD DRAWINGS
THESE RECORD DRAWINGS REPRESENT AS -CONSTRUCTED UPPER L 0 K D AVENUE
GENERAL: CONDITIONS TO THE BEST OF MY PROFESSIONAL
L-17.57
1. THE SCOPE OF THIS PROJECT INCLUDED THE INSTALLATION OF A 1250 GALLON SEPTIC TANK AND ABSORPTION TRENCH TO KNO.. JUNE 28, 2022 L-45,54 R-30.00
SERVE THE PROPOSED FOUR BEDROOM RESIDENCE LOCATED ON THE REFERENCED PROPERTY. DESIGN CRITERIA: '"� R`50,00
2. CONSTRUCTION WAS COMPLETED, TO MY PROFESSIONAL KNOWLEDGE, AS SHOWN HERE -IN, IN ACCORDANCE V.I7H THE 4 BEDROOM = 6Q0 CPD DATE:
APPROVED SITE PLAN AND DESIGN DRAWINGS. MUNICIPAL PERMIT WITH ANY SPECIAL PROVISIONS OR CONDITIONS, AND ALL - -
APPLICABLE STATE AND MUNICIPAL WASIEVIA TER DISPOSAL REGULATTONS. SOILS: 1.2 GPD/SOFT TIMOTHY LEY, PE
/ i�azo
3. UPON COMPLETION OF THE SYSTEM, M 600/1.2 = 500 SOFT
E CONTRACTOR STABILIZED THE FINISH GRADE PATH HYDRAULICALLY APPItfO BONDED
F78ER 14ATR/X MULCH AND SEED. THE PROPERTY OWNER VALL 8£ COMPLETING FUTHER LANDSCAPING IMPROVEMENTS AT A TRENCH INSTALLED PER DESIGN:
LATER DATEEFFEC �.,L ,• }
SEP RC TANK /NSTALLA 77ON.• 6' K707H Ir DEPTH
s
2' 707N
L A SEP77C TANK WAS CONSTRUCTED CONSTRUCTED BY GREER WITH A 20' RISER FOR THE FIRST COMPARTMENT AND A 4' 45' LENGTH
CLEANOUT FOR THE SECOND COMPARTMENT. PROPERTY AND NEIGHBORING PROPERTIES SERVED BY
_
2. ALL STANDPIPES/RISER ON THE SEP77C TANK WERE EXTENDED A MINIMUM OF 12 INCHES AHOY£ FINAL GRADE. TANK RISER AWWIJ WATER SYSTEM.
WAS SET AT FINAL GRADE, WITH POSITIVE DRAINAGE AROUND THE PERIMETER OF RISER COVER. APPROXIMA IF LOCATION OF THE WATER SERVICE TO THIS LOT IS SHOVAN HEREIN.-
__,.___.:_..--- 10' T&E EASEMENT }
J. SEPTIC TANK WAS INSTALLED WITH GREATER THAN 4' OF COVER. A FOUNDATION CLEANOUT WAS INSTALLED t2' FEET FROM THE NO WELLS EXIST W77741N 200' OF SEPTIC SYSTEM. 1
BUILDING FOUNDATION. IN 7N£ LINE BETWEEN 7H£ TANK AND THE L£ACHAELD TWO CLEANOUTS WERE ISNTALL£0. THESE CLEANOU7S
WERE LOCATED ON UNDISTURBED SOIL NOT MORE THAN 10' FROM 7Nf TANK. THE FIRST CLEANOUT, 1N LINE, TO CLEAN TOWARD THE
LEACHFI£LD. THE SECOND CLEANOUT TO CLEAN TOWARD THE SEPTIC TANK. L=17.57 -•r,
4. FINAL GRADING OVER THE SEPTIC TANK WAS COMPLETED TO PROVIDE POSITIVE SLOPE AWAY FROM THE SEPTIC TANK. -.,_
T= .. R=30.0 ..
1
". WATER cR�9CR LOCATiCN APPRX�liATE-'"`�
'TEMP BENCHMARK\ � '- � ) � •"
\ fffJBLDG, CORNER REFERENCE HUB \"�-If
ABSORPTION TRENCH/ORAINFl£LO INSTALLATION: / ELV = 806.95
,
5. ABSORPTION TRENCH WAS COMPLETED /N LOCATION SHOWN HEREIN THE BOTTOM OF THE EXCAVATION WAS WITHIN 2 INCHES OF
LEVEL. SIDE WALLS OF THE TRENCH WERE ROUGHED AS NEEDED PIOR TO PLACEMENT OF DRAIN ROCK
6. AFTER DRAIN ROCK WAS ISNTALLfD, THE D/SIR/BUTTON PIPE WAS LAID LEVEL WITH THE P£RFQRA TONS FACED DOWNWARD. GRAVEL
WAS THEN PLACED OVER THE DISTRIBUTION PIPE TO PRONDf A MINIMUM OF 2 NICHES OF COVER OVER THE PIPE.
7 A SILT BARRIER WYAS INSTALLED BETWEEN THE FINAL GRAVEL LAYER AND THE NATIVE SOIL BACKFILL. THE SILT BARRIER COVERD y
THE ENTIRE GRAVEL SURFACE BEFORE PLACING BACKFILL. { �\
H. MONITOR TUBES ARE FOUR (4) INCH DIAMETER AND INSTALLED APPROXIMATELY IN THE LOCA77ONS SHOWN HERIN. THE PORTION OF rl
p
THE MONITORING LUBE EXTENDINGISE THROUGH THE GRAVEL WA5 PERFORA IED FROM IHE BOTTOM OF THE TRENCH 70 THE INVc'RT Of• � --- � .'' O- PROPOSED BLDG
THE OfS7R/BUTION PIPE THIS IS EQUIVALENT TO THE EFFECTIVE DEPTH OF THE GRA VEL AS N07ED ON THE DESIGN. \ 30' TEST HOLE RA01}/g 1
BACKFILL OVER THE TRENCH IS GREATER THAN 4' DEPTH
V-
9..
_ GFF = 816,42
`r/
1dAT£RIAL SPfCIFICA7/ONS \ -� .. -- __ ,_ - --
tO, A 1,250 GALLON HDPE TANK MANUFACTURED BY GREER TANK IN ACHORAGE WAS INSTALLED.
11. ALL PIPING INSTALLED WAS 4" PVC ASTM 3034. PERFORATED PIPE WAS USED FOR THE ORAINF/LED AS SHOWN.�,6?\ ^ \ / 4"-6 CLEANOUT IE=797.24
12. SEP77C TANK INLETS AND OUTLETS WERE FITTED WITH WATER77CHT COUPLINGS (CAULDER, FERNCO, OR EQUAL). '
A5�Y / -..,,` 5,75 LF 4"-© PVC SS PIPEn`
Al - "-0 PVC SS PIPE --V ---
13. A PERMEABLE NONTOXIC SILT BARRIER (TYPAR 3401, M/RAF) 140/N, OR EQUAL) WAS INSTALLED BETWEEN THE FINAL LfACHRELD �N �"` \\ 45'/6' ED DEEP TRENCN� ••-^`��- ""-- -'-
GRAVEL LAYER AND THE NATIVE SOIL BACKFILL. •'^•IE=796.14
74. ALL LEACHFIELD GRAVEL (SEVWfR ROCK) WAS 0.5"-2.0" SCREENED GRAVEL WITH LfSs THAN i9. PASSING THE {200 SIEVE
6.90 LF 4"-0 PV_ SS PIPE
SS
OLERA `-4' 0-90'
ELBOW IE -797.135 `^
_....�
_._
.60 LF 4 -0 PITC 55 PIP,.
�10
23
...._. E..
`"
REPLACEMENT ABSORPTION AREA
(PRIOR TO REPAIR AND USE OF THE REPLACEMENT
`- TANK INLET IE=796.65
�•-' >_-
'--
AREA, A TEST HOLE AND PERCOLATION TEST WILL BE
"'TATK
OUTLET IE=796.49
REQUIRED TO VERIFY DESIGN REQUIREMENTS
4" 0-45' ELBOW IE=796.28
'
4"-0 DOUBLE CLEANOUT IE=796.45
6.56 LF 4"-0 PVC SS PIPE
•
5O
ANY VEGETATION THAT IS DISTURBED DIRECTLY DOWN
GRADIENT FROM ABSORPTION SYSTEM SHALL BE
REPLACED WITH EROSION CONTROL VEGETATION
y --._._ ---- �-_.._.,
PROPOSED BLDG
ADDITIONAL PERCOLATtota TEST LOCATION, SEE LOG DATED 6/23/2021
_-
- -
GFF =
816.42
-__.__-_,_ _
__ - ____-
__
NEAREST WELL LOCATED
a4' IT"
_„_-_"-
,_. LOT 2
------41,811 Sq. Ft.
60 Acres
S
-
`\
V
N89'5Y1t'B' 397.18'
20' DRAINAGE EASEMENT
N89'57'11'W 397.18' ,° ��
CO/MT SWING -TIES
J7 sassT
'AS MEASURED ONSITE
o /o zo
_\\y
'(�....._,qS 11
LAURA TREJO
20900 UPPER LOWLAND AVE.
TREJO RESIDENCE
FIELD BOOKS BM N0. LOCATION ELEV. DATA ¢, DATA a'"' s. REVI DATE - DESCRIPTION BY REV ig`P' •y+j
SEPTIC RECORD DRAWING
DESIGN: BASE TBC TELEPHONE --- �'k• '•*+l
t1Z�
TOPOGRAPHY TBG ELECTRIC --- 3••::•• ••.:_;
STARING: PROFILE ___ CABLE N ---g tC in
SANITARY SEWER
---
TRAFFIC SIGNAL ---
�npant,
801 E�SJtehgyPlae 10
A
othy J. ty'
CE14368
r(1
EAGLE RIVER, AK
.'ry.
STORWATEM SEWER h o -52 - 11" '`gneL
aESIQUA
CONTRACTOR: BASIS OF DATUM: ___ RE5 TBC L1cen>.e No. C
HDR. 1'=24'
SCALE
VER' N/A
06/23/22 GRID: N/A
C"�
SHEET C,2
INSPECTOR: GAS
JDALE:
STATUS: CONSTRUCTION DRAWINGS
CONSTRUCTION RECORD VERTICAL DATUM PLAN CHECK REVISIONS CONSULTANT SEAL
0 TEMP. BENCHMARK REFERENCE POINT
FOR NORTHWEST FOUNDATION CORNER
SEPTIC SYSTEM PROFILE
NO
TUBES IN
LINE
-------------
-_
795
FROM 4"a SOLID PVC
---F785
RECORD DRAWINGS
THESE RECORD DRAWINGS REPRESENT AS -CONSTRUCTED
CONDITIONS TO THE BEST OF MY PROFESSIONAL
KNOWLEDGE AS -0 28, 20 2.
DAT *Z-
TlMf5-THY
ALLFy PE
TREJO RESIDENCE
FIELD BOOKS BM NO. LOCATION ELEV. DATA M er" DATA - s. REV DATE DESCRIPTION BY REV ,iy'�P
DESIGN: BASE TBG TELEPHONE --- *: * LAURA TREJO
STAKING: ---
PROFILE
TBC CABLE TV --- g�
,„, �((t G, P,�Y �� m IhY, II�� 20900 UPPER LOWLAND AVE. SEPTIC PROFILE
SANITARY SEWER --- TRAF'fiC SIGNAL --- 801 E 34It�h 10 �''No. CE ;" /
-eua T: STORM SEWER --- DESIGN TBC ^ ++,, ";T EAGLE RIVER, AK RECORD DRA WING
DATE: 0 C2
CONTRACTOR: BASIS OF DATUM: WATER --- QUANTITIES TOC yOR_ i�_t0• /28/22 GRID: N/A
INSPECTOR, GAS --- SCALE VER. 1^=5• SHEET
CONSTRUCTION RECORD VERTICAL DATUM PLAN CHECK REVISIONS CONSULTANT SEAL STATUS: CONSTRUCRON DRA"NGs C2
X
LLJ
< w U�
m <
Z ISVHcJ
Z w <
:E w
NOISIAi(ions SGNV�dn LJ Z) C, <
CD P= m
.................. t< 8. CX !XQ <<
'p, w
Lj <
Q) 0
2 :E
— - — - — — At\ I co
7w7v 2: —r- K
--------------------- C
'21,z6f M,,II,Zg.62N o 4, Q-. -..s V)
EL E r- I 01=1
M , 0-00
ci u
2! 'm o 2f 00- 1 0 -C > 0 V)
OE
LLJ LLJ
LL-D� g a
(U 1-00 L) -C C)
P, Ck- C 0 0)
>, - -aQ)
to �t 0 _r_ z -C =
e 0- 0 U ui t
W O.0 :Z)
aw > LL <
WSW a) o 0
__p c -a -�2 -� . 80_6 0
tgl) — C) (, , =, .. , ,
LL, R LLJ c)
c, 2 oc ;--z n
2 E -0.0' Z
CQ- ot.-
C:
ul --o <
0 0 F
002--- <, 16 �S
0) (0,-0 CLv <
J- L :3 0-0 -1
— . E , O.E
C�"Nzl
Ab W
1, ti 0 0 0- CN n
z
CD w Cc g
LL o
I V3(:j loe 0 V) C 0 0 > LLJ
2 vi
C) :lj- AO& n
bcl 1) L) 0
-3 LLJ 0
C2
> C,
-C
CL -K �K C) -,Q x g 0
w (01 ..-2 :V:)) rL
CS
Z,
w
................. F-
. O09 ... ........
.. ....... . Q
0
LO m
69 z
D.... C)
...... z
. ....... . ...............
n C) . ........
C) "**' -- .... I "- V--
................ 7-%-.Ln
....... ...... .................... ......
.... Lo
........ ....... ............ a)
.. .
LO
4=1 C\j
.. ...............
---r— C\l
0
............... 0
........... -j
LO
..............
cu
0
0 U-
CN 0,0
Ma 'm
... ... ......
0 EL-
0
ur) mD :E
IV, I,-
.........
0 U-)
lz
<
ap co 'S
I Ij C: Q
:pe CD z
C? w
0
co
a:
a.
t+ :ts moi„
Alaska 99654
June 28, 2022
On-site Water & Wastewater Section
Development Services Department
Municipality of Anchorage
4700 Elmore Road
Anchorage, AK 99507
RE: Request for Waiver not Submitted with COSA or Permit
Uplands Subdivision Phase 3 Lot 2
On behalf of Laura Trejo, The Boutet Company has prepared the attached record drawings in pursuit of
an approval to operate a domestic onsite wastewater system. During construction, the system was
shifted approximately 1.5 feet to the west to accommodate the plumbing in the interior of the
foundation. The system construction was completed as designed resulting in a 8.5 foot separation from
the end of the absorption trench and the western property line (See attached Record Drawings).
The approval of this waiver will have little to no impact on the adjacent property. The absorption trench
has an effective depth of 6' requiring a separation of 12' from adjacent trenches. This separation is
maintained due to the remaining 8' separation from the end of the trench to the property line and the
required 10' separation from the future septic on the adjacent lot to the property line.
On behalf of the owner, Laura Trejo, I hereby request approval of this waiver and to operate the septic
system for the subject property. I am happy to answer any further questions that you may have and look
forward to your response.
Sincerely,
Tim Alley, PE
Civil Engineer
The Boutet Company, Inc.
Office: (907) 357-6760
Mobile: (907) 830-2821
Email: talley@tbcak.com
Attachments:
Waiver not Submitted with COSA or Permit Form
Septic System Inspection Report
Septic System Record Drawing Plan
Septic System Record Drawing Profile
As -built Survey
Municipality of Anchorage
n�s°
P.O. Box 196650 • 4700 Elmore Road
Anchorage, Alaska 99519-6650 a (907) 343-7904 • Fax (907) 343-7997
http://www.muni.org/Onsite
Development Services Division
On -Site Water and Wastewater Program
* * * * VARIANCE/WAIVER REVIEW * * * *
Waiver#: OSV221044 COSA
PID#: 050-474-65
Legal Description: Uplands # 3
Engineer: Timothy Alley
Applicant: Laura Trejo
Permit#: OSP211215
Your request for a waiver of the required 10 feet horizontal separation from the drain field to the
lot line has been approved. The approved separation distance is 8.
This waiver approval applies to the Existing Trench only. Any future upgrade to the on-site
wastewater disposal system will require all separation distances be met or another approval from
this department
❑The affected adjacent property owner(s) have been given a 7 -day notice regarding this
waiver.
❑ Notarized letter(s) of nonobjection have been received from the owner(s) of the affected
adjacent property.
[%� Adj acent properties are not affected by this waiver.
Waiver is Granted: X Waiver is not Granted:
Date: [ �v Approved b .
Name of R viewer
**** VARIANCE/WAIVER REVIEW ****
�.2 Z �3- ( -,i J 7 �S�zo 2 ?__
E d1'7q
MUNICIPALITY OF ANCHORAGE
On -Site Water & Wastewater Program
PO Box 196650 4700 Elmore Road
Anchorage, Alaska 99519-6650 Phone: (907) 343-7904 Fax: (907) 343-7997
http://www.muni.org/onsite
On -Site Wastewater Disposal System Permit
Permit Number: OSP211215
Work Type: Septic Initial
Tax Code Number: 05047465000
Site Legal Address: UPLANDS PH 3 LT 2 G:0057
Site Mailing Address: 20900 UPPER LOWLAND AVE, Eagle River
Owner: SMITH PHYLLIS FAMILY IRREVOC
Design Engineer: TBC INC
This permit is for the construction of:
Effective Date:
Expiration Date:
went
`o Srh
� n
s
Ueparnnent
Lot Size in Sq Ft:
Total Bedrooms:
6/17/2021
6/17/2022
41811
Q Disposal Field Q Septic Tank ❑ Holding Tank ❑ Privy ❑ Private Well ❑ Water Storage
All construction shall be in accordance with:
1. The attached approved design.
2. All requirements specified in Anchorage Municipal code Chapters 15.55 and 15.65 and the State of Alaska
Wastewater Disposal Regulations (18AAC72) and Drinking Water Regulations (18AAC80)
3. The wastewater code requires inspections during the installation. The engineer shall notify the Development
Services Department per AMC 15.65. Provide notification by calling (907) 343-7904 (24/7).
4. From October 15 to April 15, a subsurface soil absorption system under construction during freezing weather
shall be either:
a. Opened and Closed on the same day, or
b. Covered, sealed, and heated to prevent freezing
E
ial Provisions:
entire subsurfacedisposal field and/or alternate is not within a 30 foot radius of a percolationtest. The
eer needs to do anadditional percolation test prior to the construction of the septic field. Please submit
ed and signed results withthe As -built Inspection Report. If theresults require a design change,
ruction of the system will stop pendingOn-Site review and approval.
Received B
Issued By:
y: Date:
Date:
RUSH
MUNICIPALITY OF ANCHORAGE
Development Services Department Phone: 907-343-7904
On -Site Water & Wastewater Section �- Fax: 907-343-7997
ON-SITE SEPTIC/WELL PERMIT APPLICATION
Parcel I.D. 050-474-65-000
Property owner(s) Laura Trejo
Mailing address 19 Shelby Ranch Court, Roseville, CA 95678
Site address 20900 Upper Lowland Ave., Eagle River
Day phone 805-843-5450
Legal description (Sub'd., Block & Lot) Uplands Phase 3 Lot 2
Legal description (Township, Range & Section)
Lot Size 41,811 Sq. Ft. Number of Bedrooms 4
APPLICATION IS FOR:
APPLICATION IS AN: TYPE OF DWELLING:
(M all that apply)
Absorption Field
0
Initial 0 Single Family (SF) El
(w/wo AD U)
Septic Tank
Q
Upgrade F1Duplex (D) ElHolding
Tank
❑
Renewal ❑
Multiple Dwellings ❑
Privy
❑
(SF and/or D)
Private Well
❑
Water Storage
❑
THIS APPLICATION INCLUDES A WAIVER REQUEST FOR:
Distance:
I certify that the above information is correct. I further certify that this is in accordance with
applicable Municipal Codes.
(Signature of pe6perty owner or authorized agent)
Permit/Rush Fees: I q5%
Date of Payment:__ Z912 I
Receipt Number: 0Z61)6r-
Permit No. 05P 2 I I Z 15
Waiver Fees:
Date of Payment:
Receipt Number:
Waiver No.
GADevelopment Services\Building Safety\On Site Water and Wastewater\Forms\Client Forms\Permit Application.doc
/a,
The Boutet Company, Inc. Phone 907.357.6770
1508 E. Bogard Road, Unit #7 www.tbcak.com
Wasilla, Alaska 99654
June 15, 2021
On‐site Water & Wastewater Section
Development Services Department
Municipality of Anchorage
4700 Elmore Road
Anchorage, AK 99507
RE: Engineer Narrative On‐site Wastewater Septic System
Uplands Subdivision Phase 3 Lot 2
On behalf of Laura Trejo, The Boutet Company has prepared the following submittal in pursuit of an
approval for a domestic onsite wastewater system supporting the construction of a single‐family
residence located at 20900 Upper Lowland Avenue, Eagle River, AK; Legal description: Uplands
Subdivision Phase 3 Lot 2.
The residence to be constructed will be a 4 bedroom, approximately 4,700 square foot (sq. ft.) two story
house with a walkout basement and attached garage. The residence will be served by municipal water
and will require an on‐site wastewater (septic) system for sewage treatment and disposal.
The site topography has proven difficult for development. The entire lot slopes away from Upper
Lowland Avenue with existing slopes ranging from 25% to 45%. A drainage easement is located from the
northeast property corner to the southern property line and turns to run along the southern property
line to provide drainage to a retention area to the west. The drainage easement provides a naturally
vegetated swale for surface water to travel within to a retention/detention pond, approximately 120
from the nearest portion of the designed absorption systems.
A geotechnical investigation and percolation testing for the subdivision was completed on October 25,
2018 by Forge Engineering (geotechnical report excerpts attached). Test holes 3 and 4 were located
within the subject lot to the northwest corner. Percolation testing resulted in rates of 4 minutes per inch
and 1.16 minutes per inch, respectively. No groundwater was encountered in either test hole, nor
bedrock.
The septic system will incorporate a 1,250 gallon HDPE septic tank and 45‐foot long absorption trench
with an effective depth of 7 feet. The system has been located on the lot on a 25‐37% slope within 30
feet (ft) from test hole 4 and approximately 75 ft from the drainage way along the southern boundary.
No existing wetlands are located within 200 ft of the planned septic location. A private well is located
approximately 150’ due south of the proposed absorption system. Percolation testing was completed 4‐5
feet from existing ground surface and is approximately 3’ uphill from the infiltration trench. Due to the
onsite topography substantial fill will be required to construct the residence the infiltration trench and
septic tank will be located near the existing ground surface elevation to ensure the tank backfill does not
exceed the maximum burial depth of 10 feet. The absorption trench has been sized per the requirements
of AMC Chapter 15.65 for soil percolations rates of 1.16 minutes per inch at 1.2 gallons per day per
square foot (gpd/sq. ft.) and 150 gallons per bedroom per day. The absorption trench has been oversized
to help longevity of the system due to the location and burial depth.
The absorption system conforms to the “Steep Slope” provisions of AMC:
Slope does not exceed 46%
Adequate vertical separation distances exist.
Trench design to utilize a 24” width; less than 60”.
Plan addresses disturbed vegetation and the requirement of erosion control vegetation.
No slopes greater than 46% exist down gradient from the absorption system.
The distribution pipe is designed to depth greater than 36” below the natural organic layer.
The reserve area for a replacement absorption system is located outside of the 30’ radius of the Test Hole
#4. If/when this area is utilized, a new test hole will need to be advanced to confirm underlying soils.
The design incorporates best practices and industry standards, as well as adheres to AMC. These
practices should prove to provide a long‐lasting system, assuming proper maintenance. However, if a
catastrophic failure occurred, effluent could potentially find its way to the drainageway and being
impounded within the detention pond area. Approval from the neighboring property owner to the south
would be required to remediate such a failure. It is the opinion of this engineer, that the likelihood of
such an event is well outside the normal threshold of safety concerns.
On behalf of the owner, Laura Trejo, I hereby request approval to construct the septic system for the
subject property. I am happy to answer any further questions that you may have and look forward to
your response.
Sincerely,
Tim Alley, PE
Civil Engineer
The Boutet Company, Inc.
Office: (907) 357‐6760
Mobile: (907) 830‐2821
Email: talley@tbcak.com
Attachments:
On‐site Septic/Well Permit Application
Certificate of On‐Site Systems Approval
Test Hole Logs
Uplands Subdivision Phase 3 Lot 2 Plot Plan
Septic Plan and Details
ABSORPTION TRENCH/DRAINFIELD INSTALLATION:
6. EXCAVATE THE PROPOSED TRENCH TO THE DIMENSIONS SHOWN ON THE DESIGN. THE BOTTOM OF THE EXCAVATION SHALL BE WITHIN 2
INCHES OF LEVEL. IF THE SIDEWALLS OF THE EXCAVATION BECOME SMEARED, THEY MUST BE RAKED OR SCRATCHED (ROUGHED -UP)
BEFORE GRAVEL (SEWER ROCK) PLACEMENT.
7. ONCE THE GRAVEL IS INSTALLED, THE DISTRIBUTION PIPE IS TO BE INSTALLED LEVEL WITH THE PERFORATIONS FACED DOWNWARD.
GRAVEL IS THEN TO BE PLACED OVER THE DISTRIBU7701V PIPE TO PROVIDE A MINIMUM OF 2 INCHES OF COVER OVER THE PIPE.
8. A SILT BARRIER MUST BE INSTALLED BETWEEN THE FINAL GRAVEL LAYER AND THE NATIVE SOIL BACKFILL, ENSURE THE SILT BARRIER
COVERS THE ENTIRE GRAVEL SURFACE BEFORE PLACING BACKFILL.
9. MONITOR TUBES SHALL BE OF FOUR (4) INCH DIAMETER AND INSTALLED APPROXIMATELY IN THE LOCATIONS SHOWN ON THE DESIGN.
THE PORTION OF THE MONITORING TUBE EXTENDING THROUGH THE GRAVEL SHALL BE PERFORATED FROM THE BOTTOM OF THE TRENCH
TO THE INVERT OF THE DISTRIBUTION PIPE THIS IS EQUIVALENT TO THE EFFECTIVE DEPTH OF THE GRAVEL AS NOTED ON THE DESIGN.
10. BACKFILL OVER THE FINAL GRAVEL LAYER MUST NOT BE LESS THAN TWENTY-FOUR (24) INCHES. INSULATION MUST BE INSTALLED
WHEN THE BACKFILL DEPTH IS LESS THAN THIRTY-SIX (36) INCHES. THE FINISH GRADE OVER THE TRENCH MUST BE MOUNDED TO
PREVENT THE FORMATION OF A DEPRESSION AFTER SETTLING.
MATERIAL SPECIFICATIONS:
1. ANY SEPTIC TANK PROPOSED FOR INSTALLATION MUST BE CONSTRUCTED BY A MUNICIPALLY APPROVED SEPTIC TANK MANUFACTURER.
2. THE FOLLOWING PIPE MATERIALS ARE APPROVED FOR USE IN SEPTIC SYSTEM INSTALLATIONS IN THE MUNICIPALITY OF ANCHORAGE.
TYPE OF PIPE PERFORATED SOLID
CAST IRON YES YES
ASTM D3034 (PVC) YES YES
ASTM F810 (HDPE) YES NO
ASTM D2662 (ABS) YES YES
USE OF A TYPE OF PIPE OTHER THAN LISTED ABOVE MUST BE APPROVED BY THE INSPECTING ENGINEER.
J. INSULATION SHALL BE AT LEAST 2" THICK EXTRUDED DIRECT BURIAL POLYSTYRENE (DOW CHEMICAL COMPANY STYROFOAM HI OR
EQUAL).
4. SEPTIC TANK INLETS AND OUTLETS SHALL BE FITTED WITH WATERTIGHT COUPLINGS (CAULDER, FERNCO, OR EQUAL).
5. A PERMEABLE NONTOXIC SILT BARRIER (TYPAR 3401, MIRAFI 140/N, OR EQUAL) MUST BE INSTALLED BETWEEN THE FINAL LEACHFIELD
GRAVEL LAYER AND THE NATIVE SOIL BACKFILL.
6. ALL LEACHFIELD GRAVEL (SEWER ROCK) SHALL BE 0.5"-2.0" SCREENED GRAVEL WITH LESS THAN 17 PASSING THE #200 SIEVE.
Z WHEN SAND IS BEING USED AS A FILTER MATERIAL, ITS GRADATION SPECIFICATION MUST CONFORM TO CURRENT M.O.A. REQUIREMENTS.
INSPECTIONS:
PRIOR TO CONSTRUCTION OF SEPTIC SYSTEM, A TEXT HOLE WILL BE REQUIRED TO BE DUG CONFIRMING SOIL CONDITIONS WITHIN
PROXIMITY OF THE REPLACEMENT ABSORPTION AREA. THE ENGINEER WILL BE REQUIRED TO OBSERVE SUBSURFACE CONDITIONS AND
TO VERIFY THE DEPTH OF WATERTABLE AND ANY BEDROCK.
TYPICALLY THERE WILL BE A MINIMUM OF SIX (6) INSPECTIONS REQUIRED DURING THE INSTALLATION OF THE WASTEWATER DISPOSAL
SYSTEM. THESE INSPECTIONS WILL OCCUR AS FOLLOWS.,
1. THE FIRST INSPECTION SHALL BE CONDUCTED PRIOR TO THE START OF CONSTRUCTION AND SHALL
INCLUDE THE FOLLOWING ITEMS:
1.1. PRECONSTRUCTION MEETING BETWEEN THE CONTRACTOR AND THE ENGINEER TO DISCUSS CONSTRUCTION PROCEDURES AND DESIGN
REQUIREMENTS.
1.1. VERIFY SITE CONDITIONS CONFORM TO THE DESIGN PLANS AND PERMIT
1.2. VERIFY THE PROJECT LAYOUT CONFORMS TO THE DESIGN PLANS AND PERMIT
2. AN INSPECTION SHALL BE CONDUCTED AFTER THE EXCAVATION OF ALL NATIVE MATERIAL FOR THE DISPOSAL FIELD HAS BEEN
COMPLETED, BUT PRIOR TO PLACEMENT OF FILTER SAND AND DRAINROCK. THE PURPOSE OF THIS INSPECTION IS TO ALLOW
VERIFICATION THAT THE NATIVE MATERIAL CONFORMS TO THE SOILS LOG AND THAT THE EXCAVATION IS TO THE CORRECT DEPTH.
3. AN INSPECTION SHALL BE CONDUCTED AFTER PLACEMENT OF THE FILTER SAND, IF UTILIZED.
DESIGN: I I I I BASE I TBC I I TELEPHONE I ---
TOPOGRAPHY TBC ELECTRIC ---
STAKING: PROFILE --- CABLE TV ---
SANITARY SEWER --- I I TRAFFIC SIGNAL I ---
ASBUILT: I I ISTORM SEWER I --- I I DESIGN I TBC
I \6
I\
30' ST HOLE RADIUS - L
MAIINTAIN A MINIMUM 10"\ 602
FROMPROPERTY LINE
I \B00 J_
a \
\ 1 a
'96\112" \
\ `7 45' X 6' ED DEEP TRENCH
\ \ IE=794.50
�H3 \
- PROPOSED BLDG
CFF = 816.42 \
10'
\ \ 5.00 LF 4"-0 ABS SS PIPE_'-{ -
\ J JI
4" 0-45° ELBOW IE=795.61
5.56 LF 4"-0 ABS SS PIPE _
REPLACEMENT ABSORPTION AREA
I
PRIOR TO CONSTRUCTION OF THE PRIMARY ABSORPTION 4"-0 DOUBLE CLEANOUT E=796.86
o AREA, A TEST HOLE CONFIRMING SUBSURFACE CONDITIONS
M WILL NEED TO BE CONDUCTED. IF A DIFFERING SOIL PROFILE
/ EXISTS, CONDUCT A PERCOLATION TEST TO SUPPORT SIZING 2.70 LF 4"-0 ABS SS PIPE
OF THE REPLACEMENT ABSORPTION AREA
-----,,o
�806-
n
eoa-
\\
4" 0-90° ELBOW IE=797.18\
\ 800-
3.00 LF 4"-0 ABS SS PIPE
4"-0 CLEANOUT IE=797.24 \ \
98-
23.60 LF 4"-0 ABS SSS PIP
ANN INLET IE=797.7 �]9a
\ \-TANK-OUTLET IE=797.46
7 794 -
ANY VEGETATION THAT IS DISTURBED DIRECTLY DOWN NEAREST WELL LOCATED
GRADIENT FROM ABSORPTION SYSTEM SHALL BE 155' \ 1
REPLACED WITH EROSION CONTROL VEGETATION
-NEAREST W48', LOCATED LOT n _
N89'57'11"W 397.18'
ACgsk�911'1
/ The Bou tet Company, Inc. 'Si04,Aey: j
801 E. 57th Place x[702
Anchors a AK. 99518 ,Ly14o. C 1 368'r�
gg 5522222 55 55 1 s •0616%Zi
FxCe9Snse No52AECC957
_ 41,811 Sq. Ft.
0.960 Acres\�
20' DRAINAGE- EASEMENT J0
O
m 27 \
0
- \ 0 10 20
TREJO RESIDENCE
LAURA TREJO
20900 UPPER LOWLAND AVE. SEPTIC PLAN AND NOTES
EAGLE RIVER, AK
HOR. 1"=10' DATE: 06/16/21 GRID: N/A Cl
SCALE VER. N/A SHEET
STATUS: CONSTRUCTION DRAWINGS
UPPER L 0 WL D AVENUE
GENERAL:
4. AN INSPECTION SHALL BE CONDUCTED AFTER PLACEMENT OF DRA/NROCK, AND INSTALLATION OF DISTRIBUTION LINES, CLEANOUTS AND
L=1757
1. THE SCOPE OF THIS PROJECT INCLUDES THE INSTALLATION OF A 1250 GALLON SEPTIC TANK AND A LEACHFIELD TRENCH TO
MONITOR TUBES, BUT PRIOR TO PLACEMENT OF INSULATION, SILT BARRIER, OR BACKFILL.
- - - - - -
- - - - L-4554 - - - - - - -R=30.00 - - - - - - - - - -
SERVE THE PROPOSED FOUR BEDROOM RESIDENCE LOCATED ON THE REFERENCED PROPERTY.
R=stl.o0
5. AN INSPECTION SHALL BE CONDUCTED AFTER THE SYSTEM HAS BEEN BACKFILLED TO VERIFY
FINAL GRADING AND THE LOCATION OF - - - - -
- - - - - - - - - - - - - - - - - - -
2. CONSTRUCTION SHALL BE IN ACCORDANCE WITH THE APPROVED SITE PLAN AND DESIGN DRAWINGS, MUNICIPAL PERMIT WITH ANY
ALL STANDPIPES.
SPECIAL PROVISIONS OR CONDITIONS, AND ALL APPLICABLE STATE AND MUNICIPAL WASTEWATER DISPOSAL REGULATIONS.
6. AN INSPECTION SHALL BE CONDUCTED AFTER THE TANK IS SET IN PLACE WITH DISTRIBUTION PIPES AND CLEANOUTS INSTALLED, BUT -
-
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ANY NECESSARY UNDERGROUND UTILITY LOCATES.
PRIOR TO BACKFILL
4. UNLESS SPECIFICALLY AGREED OTHERWISE, THE PROPERTY OWNER SHALL BE RESPONSIBLE FOR ENSURING A SATISFACTORY
7. AN INSPECTION SHALL BE CONDUCTED AFTER THE TANK HAS BEEN BACKFILLED TO VERIFY FINAL GRADING, ELECTRICAL EQ U ENT
_
VEGETATION GROWTH OVER THE MOUNDED AREA.
INSTALLATION, AND THE LOCATIONS OF ALL STANDPIPES.
68
a,6\
5. CONTRACTORS INSTALLING WASTEWATER DISPOSAL SYSTEMS MUST BE CERTIFIEDTHE MUNICIPAL HEALTH DEPARTMENT FOR
SYSTEM INSTALLATIONS OWNERS INSTALLING THEIR OWN SYSTEMS MUST ALSO RECEIVE PRIOR APPROVAL FROM THE MUNICIPAL
DESIGN CRITERIA:
-\
HEALTH DEPARTMENT.
4 BEDROOM = 600 GPD
6. ALL FILL AND GRADING SHALL BE COMPLETED PER MOA CODE REQUIREMENTS
60 1.2 GPD/SQFT
600/1011 .2 = 500 SOFT
SEPTIC TANK INSTALLATION:
TRENCH DESIGN:
s(0`
10' T. E.G. -EASEMENT\
1. A SEPTIC TANK IS TO BE CONSTRUCTED BY A CERTIFIED SEPTIC TANK MANUFACTURER. ACCESS. IS TO BE CONSTRUCTED BY A
6' EFFECTIVE DEPTH
- - -
-
CERTIFIED SEPTIC TANK CONSTRUCTION SHALL INCLUDE A 20" RISER FOR THE FIRST COMPARTMENT AND A 4" CLEANOUT FOR
THE SECOND COMPARTMENT
2' WIDTH
45' LENGTH
2. THE SEPTIC TANK SHALL BE SUFFICIENTLY BEDDED TO PREVENT SETTLING OR SHIFTING OF THE TANK, REFER TO
540 SF OF ABSORPTION AREA
MANUFACTURE'S SPECIFICATIONS FOR BEDDING AND INSTALLATION REQUIREMENTS.
PROPERTY AND SUBDIVISION PROPERTIES SERVED BY
aos�
3. ALL STANDPIPES ON THE SEPTIC TANK SHALL EXTEND A MINIMUM OF 12 INCHES ABOVE FINAL GRADE. TANK RISER TO BE SET
AWWU WATER SYSTEM.
AT FINAL GRADE, WITH POSITIVE DRAINAGE AROUND THE PERIMETER OF RISER COVER.
NO WELLS EXIST WITHIN 100' OF SEPTIC SYSTEM.
4. SEPTIC TANKS INSTALLED WITH LESS THAN 4' OF COVER SHALL BE INSULATED. A FOUNDATION CLEANOUT SHALL BE INSTALLED
ONE TO FOUR FEET FROM THE BUILDING FOUNDATION. IN THE LINE BETWEEN THE TANK AND THE LEACHFIELD THERE SHALL BE TWO
ADJACENT CLEANOUTS. THESE CLEANOUTS SHALL BE LOCATED ON UNDISTURBED SOIL NOT MORE THAN 10' FROM THE TANK. THE
IT\
FIRST CLEANOUT, IN LINE, SHALL BE TO CLEAN TOWARD THE LEACHFIELD. THE SECOND CLEANOUT SHALL BE TO CLEAN TOWARD THE�
SEPTIC TANK.
TTF
\
ABSORPTION TRENCH/DRAINFIELD INSTALLATION:
6. EXCAVATE THE PROPOSED TRENCH TO THE DIMENSIONS SHOWN ON THE DESIGN. THE BOTTOM OF THE EXCAVATION SHALL BE WITHIN 2
INCHES OF LEVEL. IF THE SIDEWALLS OF THE EXCAVATION BECOME SMEARED, THEY MUST BE RAKED OR SCRATCHED (ROUGHED -UP)
BEFORE GRAVEL (SEWER ROCK) PLACEMENT.
7. ONCE THE GRAVEL IS INSTALLED, THE DISTRIBUTION PIPE IS TO BE INSTALLED LEVEL WITH THE PERFORATIONS FACED DOWNWARD.
GRAVEL IS THEN TO BE PLACED OVER THE DISTRIBU7701V PIPE TO PROVIDE A MINIMUM OF 2 INCHES OF COVER OVER THE PIPE.
8. A SILT BARRIER MUST BE INSTALLED BETWEEN THE FINAL GRAVEL LAYER AND THE NATIVE SOIL BACKFILL, ENSURE THE SILT BARRIER
COVERS THE ENTIRE GRAVEL SURFACE BEFORE PLACING BACKFILL.
9. MONITOR TUBES SHALL BE OF FOUR (4) INCH DIAMETER AND INSTALLED APPROXIMATELY IN THE LOCATIONS SHOWN ON THE DESIGN.
THE PORTION OF THE MONITORING TUBE EXTENDING THROUGH THE GRAVEL SHALL BE PERFORATED FROM THE BOTTOM OF THE TRENCH
TO THE INVERT OF THE DISTRIBUTION PIPE THIS IS EQUIVALENT TO THE EFFECTIVE DEPTH OF THE GRAVEL AS NOTED ON THE DESIGN.
10. BACKFILL OVER THE FINAL GRAVEL LAYER MUST NOT BE LESS THAN TWENTY-FOUR (24) INCHES. INSULATION MUST BE INSTALLED
WHEN THE BACKFILL DEPTH IS LESS THAN THIRTY-SIX (36) INCHES. THE FINISH GRADE OVER THE TRENCH MUST BE MOUNDED TO
PREVENT THE FORMATION OF A DEPRESSION AFTER SETTLING.
MATERIAL SPECIFICATIONS:
1. ANY SEPTIC TANK PROPOSED FOR INSTALLATION MUST BE CONSTRUCTED BY A MUNICIPALLY APPROVED SEPTIC TANK MANUFACTURER.
2. THE FOLLOWING PIPE MATERIALS ARE APPROVED FOR USE IN SEPTIC SYSTEM INSTALLATIONS IN THE MUNICIPALITY OF ANCHORAGE.
TYPE OF PIPE PERFORATED SOLID
CAST IRON YES YES
ASTM D3034 (PVC) YES YES
ASTM F810 (HDPE) YES NO
ASTM D2662 (ABS) YES YES
USE OF A TYPE OF PIPE OTHER THAN LISTED ABOVE MUST BE APPROVED BY THE INSPECTING ENGINEER.
J. INSULATION SHALL BE AT LEAST 2" THICK EXTRUDED DIRECT BURIAL POLYSTYRENE (DOW CHEMICAL COMPANY STYROFOAM HI OR
EQUAL).
4. SEPTIC TANK INLETS AND OUTLETS SHALL BE FITTED WITH WATERTIGHT COUPLINGS (CAULDER, FERNCO, OR EQUAL).
5. A PERMEABLE NONTOXIC SILT BARRIER (TYPAR 3401, MIRAFI 140/N, OR EQUAL) MUST BE INSTALLED BETWEEN THE FINAL LEACHFIELD
GRAVEL LAYER AND THE NATIVE SOIL BACKFILL.
6. ALL LEACHFIELD GRAVEL (SEWER ROCK) SHALL BE 0.5"-2.0" SCREENED GRAVEL WITH LESS THAN 17 PASSING THE #200 SIEVE.
Z WHEN SAND IS BEING USED AS A FILTER MATERIAL, ITS GRADATION SPECIFICATION MUST CONFORM TO CURRENT M.O.A. REQUIREMENTS.
INSPECTIONS:
PRIOR TO CONSTRUCTION OF SEPTIC SYSTEM, A TEXT HOLE WILL BE REQUIRED TO BE DUG CONFIRMING SOIL CONDITIONS WITHIN
PROXIMITY OF THE REPLACEMENT ABSORPTION AREA. THE ENGINEER WILL BE REQUIRED TO OBSERVE SUBSURFACE CONDITIONS AND
TO VERIFY THE DEPTH OF WATERTABLE AND ANY BEDROCK.
TYPICALLY THERE WILL BE A MINIMUM OF SIX (6) INSPECTIONS REQUIRED DURING THE INSTALLATION OF THE WASTEWATER DISPOSAL
SYSTEM. THESE INSPECTIONS WILL OCCUR AS FOLLOWS.,
1. THE FIRST INSPECTION SHALL BE CONDUCTED PRIOR TO THE START OF CONSTRUCTION AND SHALL
INCLUDE THE FOLLOWING ITEMS:
1.1. PRECONSTRUCTION MEETING BETWEEN THE CONTRACTOR AND THE ENGINEER TO DISCUSS CONSTRUCTION PROCEDURES AND DESIGN
REQUIREMENTS.
1.1. VERIFY SITE CONDITIONS CONFORM TO THE DESIGN PLANS AND PERMIT
1.2. VERIFY THE PROJECT LAYOUT CONFORMS TO THE DESIGN PLANS AND PERMIT
2. AN INSPECTION SHALL BE CONDUCTED AFTER THE EXCAVATION OF ALL NATIVE MATERIAL FOR THE DISPOSAL FIELD HAS BEEN
COMPLETED, BUT PRIOR TO PLACEMENT OF FILTER SAND AND DRAINROCK. THE PURPOSE OF THIS INSPECTION IS TO ALLOW
VERIFICATION THAT THE NATIVE MATERIAL CONFORMS TO THE SOILS LOG AND THAT THE EXCAVATION IS TO THE CORRECT DEPTH.
3. AN INSPECTION SHALL BE CONDUCTED AFTER PLACEMENT OF THE FILTER SAND, IF UTILIZED.
DESIGN: I I I I BASE I TBC I I TELEPHONE I ---
TOPOGRAPHY TBC ELECTRIC ---
STAKING: PROFILE --- CABLE TV ---
SANITARY SEWER --- I I TRAFFIC SIGNAL I ---
ASBUILT: I I ISTORM SEWER I --- I I DESIGN I TBC
I \6
I\
30' ST HOLE RADIUS - L
MAIINTAIN A MINIMUM 10"\ 602
FROMPROPERTY LINE
I \B00 J_
a \
\ 1 a
'96\112" \
\ `7 45' X 6' ED DEEP TRENCH
\ \ IE=794.50
�H3 \
- PROPOSED BLDG
CFF = 816.42 \
10'
\ \ 5.00 LF 4"-0 ABS SS PIPE_'-{ -
\ J JI
4" 0-45° ELBOW IE=795.61
5.56 LF 4"-0 ABS SS PIPE _
REPLACEMENT ABSORPTION AREA
I
PRIOR TO CONSTRUCTION OF THE PRIMARY ABSORPTION 4"-0 DOUBLE CLEANOUT E=796.86
o AREA, A TEST HOLE CONFIRMING SUBSURFACE CONDITIONS
M WILL NEED TO BE CONDUCTED. IF A DIFFERING SOIL PROFILE
/ EXISTS, CONDUCT A PERCOLATION TEST TO SUPPORT SIZING 2.70 LF 4"-0 ABS SS PIPE
OF THE REPLACEMENT ABSORPTION AREA
-----,,o
�806-
n
eoa-
\\
4" 0-90° ELBOW IE=797.18\
\ 800-
3.00 LF 4"-0 ABS SS PIPE
4"-0 CLEANOUT IE=797.24 \ \
98-
23.60 LF 4"-0 ABS SSS PIP
ANN INLET IE=797.7 �]9a
\ \-TANK-OUTLET IE=797.46
7 794 -
ANY VEGETATION THAT IS DISTURBED DIRECTLY DOWN NEAREST WELL LOCATED
GRADIENT FROM ABSORPTION SYSTEM SHALL BE 155' \ 1
REPLACED WITH EROSION CONTROL VEGETATION
-NEAREST W48', LOCATED LOT n _
N89'57'11"W 397.18'
ACgsk�911'1
/ The Bou tet Company, Inc. 'Si04,Aey: j
801 E. 57th Place x[702
Anchors a AK. 99518 ,Ly14o. C 1 368'r�
gg 5522222 55 55 1 s •0616%Zi
FxCe9Snse No52AECC957
_ 41,811 Sq. Ft.
0.960 Acres\�
20' DRAINAGE- EASEMENT J0
O
m 27 \
0
- \ 0 10 20
TREJO RESIDENCE
LAURA TREJO
20900 UPPER LOWLAND AVE. SEPTIC PLAN AND NOTES
EAGLE RIVER, AK
HOR. 1"=10' DATE: 06/16/21 GRID: N/A Cl
SCALE VER. N/A SHEET
STATUS: CONSTRUCTION DRAWINGS
CLEANOUT
MAX WATER TIGHT CAP (TYP) CLEANOUT
20" RISER WITH
— SECURABLE LID4-
ORIGINAL GRADE
4" OF UNDERGROUND
RATED INSULATION 10' MAX
"0 ABS PIPE ® 2.0% MINIMUM
INSTALL AND BED SEPTIC TANK PER
MANUFACTURE'S SPECIFICATIONS
1250 GALLON TANK-
CORROSION
MATERIAL, APPROVED
BY MOA
4"0 SOLID PVC PIPE
TRANSITION FROM 4"0 SOLID
PVC PIPE TO 4"0 PERFORATED
PVC PIPE
4"0 PERFORATED PVC
PIPE
IF DOUBLE CLEANOUT IS LOCATED BEYOND
20' OF ABSORPTION SYSTEM, A CLEANOUT IS
REQUIRED TO BE INSTALLED TO THE
ONSITE WASTEWATER SYSTEM PROFILE
CLEANOUT NOTES:
1.
MATCH PIPE SIZE AND MATERIAL PER UTILITY PLANS.
2.
DOUBLE CLEANOUT ASSEMBLY SHOWN. SINGLE CLEANOUTS ONLY
TBC
INCLUDE ONE RISER. MATCH DIRECTION OF PIPE FLOW.
3.
PROTECT CLEANOUT ASSEMBLY DURING CONSTRUCTION
FINISH GRADE
z
EAGLE RIVER, AK
SANITARY SEWER
CAP
45' ELBOW
WYE
CLEANOUT
DETAIL
DESIGN: BASE
TBC
TELEPHONE
---
TOPOGRAPHY
TBC
ELECTRIC
---
STAKING: PROFILE
The Boutet Compy, Inc.
BQ, E. 57th Ploce 702
An choggra a 55A2222K2. 559951558
FxCense
CABLE TV
EAGLE RIVER, AK
SANITARY SEWER
---
TRAFFIC SIGNAL
---
ASBUILT: STORM SEWER
---
DESIGN
TBC
CONTRACTOR: BASIS OF DATUM: WATER
---
QUANTITIES
TBC
INSPECTOR: GAS
---
CONSTRUCTION RECORD VERTICAL DATUM
PLAN CHECK
MONITORING TUBES IN
CORNERS OF FIELD
CLEANOUT
4"0 MONITORING WELL W/ REMOVABLE CAP
(TYP. 2)
4"0 PVC SS PIPE FRONT—
TANK ® 2.0%
4" DOUBLE CLEANOUT WITHIN
20' OF PERFORATED PIPE
CLEANOUT CONNECTED
TO PERORATED PIPE
MONITORING TUBES IN
CORNERS OF FIELD
PTH FROM OG TO BOTTOM OF FIELD -9' NATIVE BACKFILL
DEPTH FROM OG TO TOP OF
FINISHED GRAD FIELD > 36"
12" - 1/2"0 - 2"0 SEPTIC 4"0 SOLID PVC PIPI
DRAIN ROCK (NO MORE
THAN 1% PASSING THE
#200 SIEVE )
— — — — — - TRANSITION FROM 4"O- -SOLID
�4"0 SOLID PVC PIPE PVC PIPE TO 4"0 PERFORATED
PVC PIPE
SEPARATION FABRIC
4"0 PERFORATED PVC -,,
4"0 PERFORATED PVC-\
PIPE
12" - 1/2"0 - 2"0 SEPTIC DRAIN ROCK
(NO MORE THAN 1% PASSING THE #200 SIEVE )
4"0 PERFORATED PVC
PIPE
L -WATER TABLE
IMPERMEABLE SOILS
45'
ABSORPTION TRENCH DETAIL
(N.T.S)
4"0 END CAP (TYP)
4" CLEANOUT
z
4"0 MONITORING WELL W/ REMOVABLE CAP
(TYP. 2)
TREJO RESIDENCE
SEPTIC DETAILS
TOR. 1"=20' DATE: 06/16/21 GRID: N/A C"Z
SCALE VER. N/A SHEET
STATUS: CONSTRUCTION DRAWINGS C'Z
OF aGgs�111
�P
LAURA TREJO
041:
20900 UPPER LOWLAND AVE.
The Boutet Compy, Inc.
BQ, E. 57th Ploce 702
An choggra a 55A2222K2. 559951558
FxCense
:T'qq j
,�'fNo_ CF, 1 36S•�/
t' �0,6 16/Zi
t'�'�AiOfE"`�
EAGLE RIVER, AK
9SNo52AECC957
CONSULTANT
SEAL
4"0 END CAP (TYP)
4" CLEANOUT
z
4"0 MONITORING WELL W/ REMOVABLE CAP
(TYP. 2)
TREJO RESIDENCE
SEPTIC DETAILS
TOR. 1"=20' DATE: 06/16/21 GRID: N/A C"Z
SCALE VER. N/A SHEET
STATUS: CONSTRUCTION DRAWINGS C'Z
DEPTH
(feet)
1-
2
4
5
6
7
8
9
10-
11-
12-
13-
14-
15.
16-
17
18-
19.
20
SOILS LOG AND PERCOLATION TEST
FNGIN FF RING
LEGAL DESCRIPTION: UPLANDS TRACT I LOT 2
PERFORMED FOR: THE BOUTET COMPANY INC.
DATE: 10/25/18 PROJECT No.:
PARCEL ID#: PROPERTY ID TECHNICIAN: J. MILLETTE
TEST HJ. WILLIAMS
OLE 3
Rim
SLOPE
SITE PLAN
SEE SITE PL,�N n
2
COMMENTS:
DATE
READING
WAS GROUND WATER ENCOUNTERED? NO
NET TIME
(MINUTES)
DEPTH TO
WATER
(INCHES)
NET DROP
(INCHES)
IF YES @ WHAT DEPTH? -
L
1
2:48/2:58
DEPTH OF WATER AFTER MONITORING: NONE
0
216-
2
DATE OF MONITORING: 11/4/18
P
616/816
216-
3
3:14/3:24
10
616/$16
216
COMMENTS:
DATE
READING
GROSS TIME
(MINUTES)
NET TIME
(MINUTES)
DEPTH TO
WATER
(INCHES)
NET DROP
(INCHES)
11/23/18
TEST HOLE PRESOAKED PRIOR TO TESTING:
1
2:48/2:58
10
6 0/816
216-
2
3:02/3:12
10
616/816
216-
3
3:14/3:24
10
616/$16
216
4
3:25/3:35
10
616/$16
216
5
3:36/3:46
10
616/$16
216-
6
3:47/3:57
10
616/$16
216-
PERCOLATION RATE: 4 (MIN/INCH) PERC. HOLE DIA. 6 (INCHES)
TEST RUN BETWEEN: 4 FT. and 5 FT.
DEPTH
(f'cet)
1 -
SOILS LOG AND PERCOLATION TEST
E N G I N E E R I N G
LEGAL DESCRIPTION: UPLANDS LOT 2
PERFORMED FOR: THE BOUTET COMPANY INC.
DATE: 10/26/18 PROJECT No.:
PARCEL ID#: TECHNICIAN: J. MILLETTE
J. WILLIAMS
TEST HOLE 4
•
4
5
6
7 GM (SANDY SILTY GRAVEL)
O •`
SITE PLAN
SEE SITE PLAN
1
READING
GROSS TIME
(MINUTES)
WAS GROUND WATER ENCOUNTERED? NO
DEPTH To
WATER
(INCHES)
NET DROP
(INCHES)
'""?`
TEST HOLE PRESOAKED PRIOR TO TESTING:
IF YES Ca, WHAT DEPTH? -
L
2:56 / 3:03
1 1
6/12
6
DEPTH 01: WATER AFTER MONITORING: NONE
0
3:05/3:12
6:47
6/12
6
DATE OF MONITORING: I I-4-18
P
3:17/3:24
6:50
..1
6
E
3:27/3:34
12
13
1
1
16
17
18
19
20
COMMENTS:
DATE
READING
GROSS TIME
(MINUTES)
NET TIME
(MINUTES)
DEPTH To
WATER
(INCHES)
NET DROP
(INCHES)
11/23/18
TEST HOLE PRESOAKED PRIOR TO TESTING:
1
2:56 / 3:03
6:45
6/12
6
2
3:05/3:12
6:47
6/12
6
3
3:17/3:24
6:50
6/12
6
4
3:27/3:34
6:51
6/12
6
5
3:38 / 3:45
6:52
6/12
6
6
3:48/3:55
6:51
6/12
6
PERCOLATION RATE: 1.16 (MIN/INCH) PERC. HOLE DIA. 6 (INCHES)