HomeMy WebLinkAboutCANYON VIEW ESTATES S12747CANYON VIEW ESTATES SUBDIVISION
SEPTIC ANALYSIS &
Hultquist Homes, INC.
12580 Old Seward Highway
Anchorage, AK 99515
Prepared By:
REV October 2023
Prepared By: Grant Mathews, P.E.
* • t{ /TH
W1W V}V. MWHIEVVS
�'•• CE 135444 ,•
AW
Project Location
The project site consists of an existing 3.5-acre parcel zoned R-10SL and identified as Tract 1, Block 1, of Canyon View
Estates Subdivision. The parcel is located north of Canyon Road in Anchorage, Alaska. The site is accessed via De Armoun
Road, to Upper De Armoun Road, to Canyon Road. Surrounding properties include a mix of undeveloped and developed
residential single-family housing.
Existing Conditions & Land Cover
The site is currently undeveloped and well vegetated with mature trees and brush. Topographically, the site drains in a
westerly direction. Roughly 60 feet of relief occurs from the southeast corner to the southwest. The average slope across
the parcel is 10-15%.
Proposed Development Plan
The proposed development intends to subdivide and create two residential lots from the 3.5-acre parcel. Each lot will be
served by individual wells and onsite septic systems as no public water or sewer infrastructure exists within the area. Lot
14 is 1.7 Acres and Lot 15 is 1.8 Acres. Access to each of the lots will be directly from Canyon Road. Existing grades are
generally less than 25% across the site, and the proposed lot sizes exceed the 40,000 SF minimum lot size required to
support onsite systems.
Testing Process
Triad Engineering, LLC performed septic testing onsite on August 30th, 2023. Weather conditions were generally cloudy
and damp with temperatures in the mid-50's in the morning to mid-60's in the afternoon. Brownson Bros., LLC mobilized
a 200 series excavator to the site and provided an operator for the geotechnical exploration.
Test holes were staked by S4 Group in advance of testing. Access for the excavator was such that minimal to no clearing
was required for testing. Each test hole was advanced to a depth of roughly 16 feet below ground surface (BGS). Upon
completion of each test hole, a 4-in diameter perforated pipe was placed within the excavation and backfilled with the
stockpiled soils.
A bench was excavated adjacent to each test hole at an appropriate elevation so that percolation testing could be
completed. A roughly eight -inch -deep hole was hand dug into undisturbed soils using a shovel and approximately two
inches of 3/8" pea gravel was placed at the bottom of the hole. A four -inch diameter perforated PVC pipe was placed
vertically into the test hole and the annulus backfilled with pea gravel. Water was then carefully poured into the pipe to a
level approximately six inches above the bottom of the hole. Measurements were then taken using a standard tape
measure. The process was repeated for each test hole as necessary to meet Title 15 requirements. The initial reading in
all test holes exceeded %" drop, so pre-soaking was not required.
The investigation proceeded from north to south, with Lot 15 being completed first and Lot 14 completed last. Free
groundwater was not encountered during the investigation, but surficial weeps were encountered.
Soils
Soils encountered during the investigation were visually classified in general accordance with the Unified Soil Classification
System (USCS). The general subsurface profile encountered for both Lots 14 and 15 consisted of approximately 12 inches
of surficial organics followed by 15 feet of dense, silty gravel.
Bedrock
Bedrock was not encountered during the investigation and is not anticipated to negatively impact future development of
the lots.
Percolation Test Results
Below is a summary of the percolation test results by lot and the subsequent reserve areas required. See the attached site
plan for test hole locations on each lot.
Table 1- Septic Testing Results Summary
Lot
Perc Rate
Depth of TH
Groundwater
Groundwater
Reserve Area (ft')
(min/in)
(Initial)
Monitoring (Oct'23)
Lot 14
<1
16'
NGWE
10.5' BGS
10,000
Lot 15
<1
16'
NGWE
10.5' BGS
10,000
Groundwater
During the initial investigation, no groundwater was encountered. Subsurface flows were encountered as weeps in the
sidewall of the excavation at approximately 10-ft BGS in TH-15A. The subsurface flows were deep enough that they did
not affect the perc testing. It is unlikely that the water table would negatively impact future septic systems based on our
field observations. Seasonal changes to the water table elevation are expected to occur due to rainfall and snow melt
runoff. Groundwater monitoring in October 2023 found groundwater at 10.5-ft BGS in both test holes.
Water Availability
The MOA's COSA database was reviewed to assess water availability in the immediate vicinity of the proposed subdivision.
The properties surrounding this parcel are largely undeveloped. However, the five closest properties with published data
were found to have flow rates of 6-20 gpm. A summary of those rates are as follows:
Parcel ID
Drill date
Well depth
Static Water Level
Production
Nitrate Levels (mg/L)
021-021-36
10/12/22
206 ft
154 ft
6 gpm
1.61
021-021-48
11/11/22
206 ft
103 ft
20 gpm 2.93
042-081-03
4/12/05
225 ft
37 ft
4 gpm
4.08
042-081-IC)
10/21/93
106 ft
38 ft
6 gpm
3.16
042-081-16
8/28/80
140 ft
27 ft
6 gpm
2.27
Based on the available data, well production is not a concern for the proposed lots and no negative impacts to the well
flows of adjacent properties is anticipated with the development of this subdivision. All nitrate readings in the immediate
vicinity are less than 5 mg/L.
Steep Slope Development
A portion of the reserve area for Lot 15 is in an area with natural slopes ranging from 25%-30%. If a septic system is
installed in this area, it will need to comply with 15.65.210.B.4.
Steep slope disposal fields. Except as modified by this subsection, steep slope disposal fields shall comply with this chapter.
a. General. A deep trench or non -mounded wide trench disposal field may be instaslled on a slope greater than 25
percent, but less than 46 percent, if it complies with all of the following conditions.
Vertical separation distances below the disposal field shall be measured from the bottom of the droinrock
at the up-grodient side of the disposal field.
This condition can be met.
ii. Trenches shall not exceed 60 inches in width.
This condition can be met.
iii. Natural vegetation within 50 feet down -gradient of the disposal field shall remain undisturbed, or the
exposed slope shall be stabilized with erosion control vegetation or an approved equal prior to final
operational approval.
This condition can be met. The large lot size allows for natural vegetation to be retained, or the disturbed
areas can be revegetated.
iv. The distribution pipe invert shall be a minimum of 36 inches below the top of the natural organic surface,
measured on the downhill side of the trench. (See chapter 15 for exceptions)
This condition can be met.
V. The disposol field shall be a minimum of 100 feet up -gradient from any slope exceeding 46 percent. (See
chapter 15 for exceptions)
This condition can be met. The slope on the property does not exceed 30% and all slopes downgradient
of the lot within 100-ft are less than 30%.
Conclusion
In summary, perc test results indicate that both proposed lots contain soils capable of supporting on -site septic systems.
Well -draining soils were encountered for both Lots 14 and 15. Groundwater was measured at 10.5-ft BGS during the
month of October, when groundwater is typically at a seasonal high. Review of available well log information indicates
that water is abundant in the area with an average production around 6 GPM.
Thank you for your time and consideration in this matter. If you require additional information, please call 907-720-6128
or email me at grantmathews@triadak.com.
Sincerely,
Triad Engineering, LLC
7:1___
Grant Mathews, P.E.
Attachments: Grading Plan
Perc Test Results
Municipality of Anchorage
Development Services Department
On -Site Water and Wastewater Section
47uoElmore St.
po.Box 1esosuAnchorage, Anoyo1s-ssau
Soils Log - Percolation Test
Performed For: Cody Hultquist Date Performed: 8-30-2023
Legal Description: Canyon View Estates Lot 14 Block Township, Range, Section: NIA
0
5-
6-
7-
8-
A-
10-
11-
12-
13-
14-
15-
1G-
17-
18-
1D-
Surface Organics
Silty Gravel (GM)
Tan.Denoo
12'Cobbles
Site Plan
NONE
MENEM
MEMEMEMEME
MEMEMEMEME
MEMEMEMMM
MMMMMMMMMM
MMIEMMMMMMM
MMMMMMMM
MMMMMMMMMM
MMMMMMMMMM
MMMMMMMMMMI
WAS GROUND WATER
cwuouwrsnsor Yes
o
IFYES, xrWHAT DEPTH? L
oq�mwate,After ----- "
Date: 10-4-2023
|
| xeamng | Date | umuo Time | Net Time | Depth mWater | Net Drop |
PERCOLATION RATE ^1 �mm�x�m penoxo�somwsrcn 8^
TEST RUN BETWEEN 3.5 pr xwo 4.5 rr
COMMENTS Added u 2 gal of water in | that / All water absorbed in les� that 5 min, Repeated 2x
------
PERFORMED BY: Triad Engineering, LLC | -Grant Mathews, P.E.CERTIFY THAT THIS WAS
PERFORMED IN ACCORDANCE WITH ALL STATE AND MUNICIPAL GUIDELINES IN EFFECT ON THIS DATE. DATE: 10-4-2023
Municipality of Anchorage
Development Services Department
On -Site Water and Wastewater Section
4700 Elmore St.
P.O. Box 196650 Anchorage, AK 99519-6650
www.muni.org/onsite
(907)343-7904
Soils Log - Percolation Test
* 4)1 TH
• • ��GRAN� W. PotATNEWS
Performed For: Cody Hultquist Date Performed: 8-30-2023
Legal Description: Canyon View Estates Lot 15, Block 1 Township, Range, Section: N/A
1-
2-
3-
4-
5-
6-
7-
10-
11-
12-
13-
14-
15-
16-
17-
18-
19-
20-
Silty Gravel (GM)
Tan, Dense
12" Cobbles
WAS GROUND WATER
ENCOUNTERED? No
S
Weeps @ 10' IF YES, AT WHAT DEPTH? L
Depth to Water After 0
Monitoring? 10.5' BGS E
Date: 10-4-2023
BOH @ 16'
(NGWE)
Site Plan
■■■■■■■■■■
■®�.
EEMEME
■■■■■■■■■■
■■■■■■■■■■
■■■■■■■■.■
■■■■■■■■■■
■■■■■■■■■■
■■■■■■■■■■
■■■■■■■■■■
Reading Date Gross Time Net Time Depth to Water I Net Drop
PERCOLATION RATE <1 (minutes/inch) PERC HOLE DIAMETER 6"
TEST RUN BETWEEN 4 FT AND 5 FT
COMMENTS Added approx. 2 gal of water in less that 2 min. Ail water absorbed in less that 6 min. Repeated 2x
PERFORMED BY: Triad Engineering, LLC I Grant Mathews, P.E. CERTIFY THAT THIS TEST WAS
PERFORMED IN ACCORDANCE WITH ALL STATE AND MUNICIPAL GUIDELINES IN EFFECT ON THIS DATE. DATE: 10-4-2023
12 v —.t
hI�
U
oo
7
10' T&E ESM T
25%-30
A
0 13 TH15A
SEPTIC 0
PC T z
z RESERVE
AREA
Pur 10,000SF I w
2016-073102-0 CF FF ELEV RECORD DRAVANG
1265 �27
t DATA PROVIDED
BY,
FF ELEV
1240 1250 that o on .... d mn
his t.O=Ufy
TWO ore a true and cocura e
r,pnee"totio, of the P"*t
SST ic 0
AP RESERVE
AREA 7 15 CONTRACTOR:
O,OOOSF 14 BY.,
A
PC F2?,I33 TllLE!_DAl[:
2. DATA TRANSFERRED
PUE
v 2016-0I304 BY:
COMPANY,
GRADING NOTESVia° I DATA TRANSFER CHECKED
Based an P111.6k nold ob-
BLDG E ln�r
i% y 1. ALL FILL SHALL BE PLACED IN ONE FOOT LIFTS, MAXIMUM, AND COMPACTED SETBACKS di,�,d..lh'
he, direct oup-ison), the
TO 95% MINIMUM AND IN COMPLIANCE WITH THE SOILS ENGINEER'S Contr-tor-pro,ided data
RECOMMENDATIONS. NO ROCK OR SIMILAR IRREDUCIBLE MATERIAL WITH A
appears to mpressnt the
MAXMUM DIMENSION GREATER THAT 12 INCHES SHALL BE BURIED OR PLACED ".ject .. con.tted.
IN FILLS. F, % ly-, 2. PRIOR TO PLACING FILL MATERIAL, THE GROUND SURFACE SHALL BE COMPANY
PREPARED TO RECEIVE FILL BY REMOVING VEGETATION. SCARIFY THE EXISTING Il WELL
GROUND SURFACE TO PROVIDE A BOND WITH THE PROPOSED FILL, ORGANIC RADIUS
SOILS MAY BE SPREAD OVER FINISHED SLOPES AND PROPOSED LOTS AT A 1ITLE: 1AIL BY.
MAXIMUM THICKNESS OF 6 INCHES.
3. PER AMCR 23.105.111.3, THE TOE OF FILL SLOPES SHALL BE MADE NOT
NEARER TO THE SITE BOUNDARY LINE THAN ONE-HALF THE HEIGHT OF THE
SLOPE WITH A MINIMUM OF TWO (2) FEET AND A MAXIMUM OF TWENTY (20) 20' T&C ESUT
FEET.
4. PER AMCR 23,105,111.2, THE TOP OF CUT SLOPES SHALL NOT BE MADE
NEARER TO A SITE BOUNDARY LINE THAN ONE -FIFTH OF THE VERTICAL
HEIGHT OF CUT WITH A MINIMUM OF TWO (2) FEET AND A MAXIMUM OF TEN z
1) FEET. THE SETBACK MAY NEED TO BE INCREASED FOR ANY REQUIRED 0
INTERCEPTOR DRAINS. V) _j
5. FILL SLOPES SHALL NOT BE CONSTRUCTED ON NATURAL SLOPES STEEPER LLI DO
THAN 1 UNIT VERTICAL IN 2 UNITS HORIZONTAL (50% SLOPE). WHERE
SLOPES ARE STEEPER THAN 1 UNIT VERTICAL IN 5 UNITS HORIZONTAL (20%
SLOPE) AND THE FILL HEIGHT IS GREATER THAN 5 FEET, A BENCH UNDER �Lj 'U2
6. HOURS OF
THE TOE OF OPERATION THE FILL SHAVOLLLL BE BE BETWEEN 6:00 A.M.A.M� TO INSTALLED AT LEAST 1010:00 FEETP.MWIDE. > Z
., A
MON.-SAT. ANY WORK SCHEDULED TO OCCUR OUTSIDE THESE HOURS OF 20' W ESWT A Z <
OPERATION WILL REQUIRE A NOISE PERMIT PER AMC 15.07.070. 0
7. FILL CUT SLOPES TO BE 2:1 MAX. >- f2 0
8. THE CONTRACTOR SHALL MAINTAIN OPEN AND UNOBSTRUCTED ROUTES DAILY z
UNTIL CONSTRUCTION IS COMPLETE.
0
<
9. NO FILL MATERIAL WILL BE PLACED IF FROZEN AND NO FILL SHALL BE 0
PLACED ON FROZEN MATERIAL.
10. A RIGHT OF WAY PERMIT IS REQUIRED FOR ANY WORK WITHIN THE MOA
RIGHTS OF WAY.
11. MAINTAIN POSITIVE DRAINAGE PATTERNS AWAY FROM THE BUILDINGS.
12. AFTER GRADING IS COMPLETED, STABILIZE ALL DISTURBED AREAS.
10
11 FINISH FLOOR ELEVATIONS REFLECT AN APPROPRIATE RANGE OF ELEVATIONS
NEEDED TO PROVIDE MODERATE DRIVEWAY GRADES AND MODERATE BUILDING
SITE CUT OR FILL. THE FINISH FLOOR ELEVATION MAY VARY DUE TO THE
SLOPING TOPOGRAPHY OF THE SITE AND THE LAYOUT/PLACEMENT OF THE
HOUSE ON THE LOT, PUE
14. DRIVEWAYS ARE NOT TO EXCEED A 10% GRADE WITH A MINIMUM 10' LANDING 20t6-01JI02-0
CL
OF NOT MORE THAN 2% WHERE THE DRIVEWAY INTERSECTS THE ROADWAY.
z
0
Ln
GRAPHIC SCALE �i
a:
50 0 25 50 IDO 200
IN FEET
I INCH =y FT.
uu
100