HomeMy WebLinkAboutTAILWIND S12719Onsite File
Prepared for:
LAND LLC
Prepared By:
ENGINEERING,LLC
P.O. Box 111989
Anchorage, Alaska 99511
(907) 561-6537
••a, •m
REV October 2023
Prepared By: Grant Mathews, P.E.
-00'-oF A "'A
TH
CE 135444
2
PR 0 *F E'SS
Project Location
The project site consists of an existing 2 -acre parcel with a single-family home in South Anchorage, at the northwest
intersection of Flyway Ave and Gander St. Surrounding properties include a mix of residential single-family housing. The
property is bordered by Kempton Hills to the south with public water and sewer utilities. The parcels to the east, west,
and north are 1 -acre plus lots with on-site water and wastewater systems.
Existing Conditions & Land Cover
The site contains an existing single-family home, garage, and driveway but is otherwise well vegetated with mature trees
and brush. Topographically, the site drains in a southwesterly direction. Roughly 30 feet of relief occurs from the northeast
corner to the southwest. The average slope across the parcel is 10-15%.
Proposed Development Plan
The proposed development intends to subdivide and create two residential lots from the 2 -acre parcel. One lot will retain
the existing single-family home, well, and septic system that serves it. Each lot is roughly 1 -acre. Existing grades are less
than or equal to 30% across the site, and the proposed lot sizes exceed the 40,000 SF minimum lot size required to support
onsite systems.
Testing Process
Triad Engineering, LLC performed septic testing onsite on July 22"d, 2023. Weather conditions were generally sunny with
temperatures in the mid -60's. Land LLC mobilized a Kubota L45 backhoe to the site and provided an operator for the
geotechnical exploration.
Access for the excavator was such that minimal to no clearing was required for testing. The test hole was advanced to a
depth of roughly 10 feet below ground surface (BGS). Upon completion of the test hole, a 4 -in diameter perforated pipe
was placed within the excavation and backfilled with the stockpiled soils.
A bench was excavated adjacent to each test hole at an appropriate elevation so that percolation testing could be
completed. A roughly eight -inch -deep hole was hand dug into undisturbed soils using a shovel and approximately two
inches of 3/8" pea gravel was placed at the bottom of the hole. A four -inch diameter perforated PVC pipe was placed
vertically into the test hole and the annulus backfilled with pea gravel. Water was then carefully poured into the pipe to a
level approximately six inches above the bottom of the hole. Measurements were then taken using a standard tape
measure. The process was repeated for each test hole as necessary to meet Title 15 requirements. The initial reading in
all test holes exceeded %" drop, so pre-soaking was not required.
Groundwater was not encountered during the investigation, but surficial weeps were encountered.
Soils
Soils encountered during the investigation were visually classified in general accordance with the Unified Soil Classification
System (USCS). The general subsurface profile encountered was sand, transitioning to silt. A test hole was dug on Lot 2,
but no hole was dug on Lot 1 since it has an existing functioning septic system with an approved COSA completed in 2023
by Garness Engineering.
Bedrock
Bedrock was not encountered during the investigation and is not anticipated to negatively impact future development of
the lots.
Percolation Test Results
Below is a summary of the percolation test results by lot and the subsequent reserve areas required. See the attached site
plan for test hole locations on each lot.
Table 1 - Septic Testing Results Summary
Lot
Perc Rate
Depth of TH
Groundwater
Groundwater
Reserve Area(
017-462-05
(min/in)
68 ft
(Initial)
Monitoring (Oct'23)
0.00
2
<1
10'
NGWE
NGWE
10,000
As mentioned, no test hole was dug on Lot 1. The lot has an existing functioning septic system and adequate space to
install a replacement drainfield. The septic tank was replaced in 2023 as part of the recent COSA approval. Soils are
anticipated to closely match those encountered during the investigation of Lot 2 based on the topography, vegetation,
and review of neighboring historical test hole data. Additionally, the existing seepage pit has functioned for over 50 years
indicating that the soils on site are well draining. A reserve area of 16,000 square feet is shown on the grading plan for Lot
1; if needed, there is adequate space on the lot for installing a new system in the future.
Groundwater
During the initial investigation, no groundwater was encountered. Groundwater monitoring in October 2023 confirmed
no groundwater in the monitoring tube.
Water Availability
The MCA's COSA database was reviewed to assess water availability in the immediate vicinity of the proposed subdivision.
The properties surrounding this parcel are largely undeveloped. However, the five closest properties with published data
were found to have flow rates of 4-20 gpm. A summary of those rates are as follows:
Parcel ID
Legal Description
Well Depth
Static Water
Production
Nitrate Levels (mg/L)
017-462-05
Tailwind, Lot 1
68 ft
26 ft
6 gpm
0.00
017-462-29
Landing Zone, Lot 2
154 ft
40 ft
10 gpm
2.18
017-462-28
Landing Zone, Lot 1
164 ft
38 ft
80 gpm
0.00
017-462-16
Drake, Blk 4, Lot 4
Unk
13 ft
4 gpm
2.81
017-462-15
Drake, Blk 3, Lot 1
82 ft
24 ft
4 gpm
6.36
Based on the available data, well production is not a concern for the proposed lots and no negative impacts to the well
flows of adjacent properties is anticipated with the development of this subdivision. All nitrate readings in the immediate
vicinity are less than 7 mg/L and most readings were less than 5 mg/L. The lots directly south of the subject property are
served by public water and sewer. A screenshot of the MOA Nitrate Values Map is shown on the following page.
Conclusion
In summary, perc test results indicate that the proposed vacant lot contains soils capable of supporting an on-site septic
system. The existing house has an approved COSA from this year, with plenty of space to install a new system at a later
date if the existing drainfield requires replacement. Well -draining soils were encountered for Lot 2 and groundwater was
not encountered during the month of October, when groundwater is typically at a seasonal high. Review of available well
log information indicates that water is abundant in the area with an average production around 5-10 GPM.
Thank you for your time and consideration in this matter. If you require additional information, please call 907-720-6128
or email me at grantmathews@triadak.com.
Sincerely,
Triad Engineering, LLC
1. J
Grant Mathews, P.E.
Attachments: Grading Plan
Perc Test Results
Municipality of Anchorage
Development Services Department
On -Site Water and Wastewater Section
4700 Elmore St.
P.O. Box 196650 Anchorage, AK 99519-6650
www.muni.org/onsite
(907)343-7904
Soils Log - Percolation Test
Performed For: Land LLC
Legal Description: Tailwind Subdivision, Lot 2
TH-1
1-
2-
3-
4-
5-
6-
7-
8-
9-
10-
11-
12-
13-
14-
15-
16-
17-
18-
19-
20 -
Organics, root mat
Silty sand, brown, SM
Sand w/ trace silt
gray -brown, SP
Silt w/ sand, tan, dense
ML
FA
*; 4,9 TH
a"{{aJ�iyr
• • • 4;A ;W. MATHEWS
�' % CE 135444
c�`PlF . • 0�'��
�11\'OPRQFESSIONP��
Date Performed: 7.22.23
Township, Range, Section:
Site Plan
e
t e
WAS GROUND WATER
ENCOUNTERED?
No
S
BOH IF YES, AT WHAT DEPTH?
N/A
L
NGWE Depth to Water After
P
Monitoring?
NGWE
E
Date:
10.12.23
Reading Date Gross Time Net Time Depth to Water Net Drop
F'LKUULA I IUN KA I E � I (minutes/inch) PERC HOLE DIAMETER 6"
TEST RUN BETWEEN 2 FT AND 3 FT
COMMENTS Added approx 2 gal of water in less than one min, all water absorbed in less than 4 min. Added approx 2 gal of water in less than one min,
all water absorbed in less than 5 min.
PERFORMED BY: Triad Engineering, LLC I Grant Mathews CERTIFY THAT THIS TEST WAS
PERFORMED IN ACCORDANCE WITH ALLSTATE AND MUNICIPAL GUIDELINES IN EFFECT ON THIS DATE. DATE: 10.12.23